Thanks to voters’ approval of a bond measure in 2018, schools all across the district are receiving expansions and/or improvements.
The district is finishing its third year of construction under the bond program. To date, 90% of architectural design work is complete, and 63% of planned construction is substantially complete, meaning the spaces are ready to be used for school operations. Fifty-four out of the district’s 60 school sites are either in architectural design, under construction, or substantially complete.
At Cummings Elementary, bond improvements were complete in the fall of 2020. Cummings received a cafeteria expansion, a secure check-in space at the front entry, heating and ventilation system improvements, seismic improvements, intercom system upgrades, a new portable classroom and a new walking path along Delight Street.
All schools in the district will receive some level of improvement under the bond. The following table gives a summary of the status of work at schools in the McNary High School feeder system.
School | Project start | Project end | Status |
---|---|---|---|
McNary High | Summer 2019 | Fall 2020 | Complete |
Claggett Creek Middle | Summer 2020 | Fall 2020 | Complete |
Whiteaker Middle | Summer 2020 | Fall 2020 | Complete |
Clear Lake Elementary | Summer 2020 | Fall 2020 | Complete |
Cummings Elementary | Summer 2020 | Winter 2020 | Complete |
Forest Ridge Elementary | Summer 2023 | Fall 2023 | Not yet started |
Gubser Elementary | Spring 2019 | Fall 2019 | Complete |
Keizer Elementary | Summer 2022 | Fall 2023 | In design |
Kennedy Elementary | Summer 2021 | Fall 2022 | In construction |
Weddle Elementary | Summer 2020 | Fall 2020 | Complete |
Many schools across Salem in the district’s five other high school feeder systems are also in various phases of construction or are complete.
Thank you, voters, for providing relief for overcrowding, increased safety and security, expanded career and technical (vocational) education opportunities, and more for our students.
For more information about the 2018 bond program, please visit www.salemkeizer.org/projects-status.